NPV數據折現率=6%期間 現金流量0 -47,238,0231 227,005,505.82 227,005,505.83 227,005,505.84 227,005,505.85 227,005,505.86 227,005,505.87 227,005,505.88 227,005,505.89 227,005,505.810 ... 顯示更多 NPV數據 折現率=6% 期間 現金流量 0 -47,238,023 1 227,005,505.8 2 227,005,505.8 3 227,005,505.8 4 227,005,505.8 5 227,005,505.8 6 227,005,505.8 7 227,005,505.8 8 227,005,505.8 9 227,005,505.8 10 227,005,505.8 11 215,500,000 12 215,500,000 13 215,500,000 14 215,500,000 15 215,500,000 16 215,500,000 17 215,500,000 18 215,500,000 19 215,500,000 20 215,500,000 IRR數據 假設資金成本=6% 期間 現金流量 0 -47,238,023 1 227,005,505.8 2 227,005,505.8 3 227,005,505.8 4 227,005,505.8 5 227,005,505.8 6 227,005,505.8 7 227,005,505.8 8 227,005,505.8 9 227,005,505.8 10 227,005,505.8 11 215,500,000 12 215,500,000 13 215,500,000 14 215,500,000 15 215,500,000 16 215,500,000 17 215,500,000 18 215,500,000 19 215,500,000 20 215,500,000 請順便解釋一下怎麼算!謝謝 更新: 期間都是0-20 其他都是現金流量 有點擠 希望看的懂..

最佳解答:

 

此文章來自奇摩知識+如有不便請留言告知

$2,367,180,682.89 = NPV 481%=IRR 這些其實很簡單, 你如果要筆算的話在網上查公式就好了 或者用excel就可以做這些問題 把數據輸進去然後 在一個空格中裏面 打 =NPV(這裏寫折現率,這裏框數據) 算IRR一樣 =IRR(這裏框數據,這裏寫假設資金成本)

其他解答:7C4150FCDCEDD023
arrow
arrow

    gpjqem1 發表在 痞客邦 留言(0) 人氣()